The High Voltage Division was tasked to figure out a substation solution for the project that could be delivered within the aggressive project schedule. After further investigation, Hunt Electric entered into a partnership with Construction Innovations, a company that was able to provide a pre-knitted modular substation solution that minimized weeks of construction time, removed typical engineering headaches, and provided on-site construction management for the majority of the project. Due to the large power demand required to run the UPS facility, the project team designed and constructed a 138KV-12.47KV 20 Mega Watt substations with (2) 10 MVA transformer to feed the (6) 4000 A interior distribution substation which is located inside the facility.